LDT Quality Management System and Change Control
LDT quality management is the set of systems that keep a laboratory developed test performing as validated after it goes live: quality control, calibration and calibration verification, proficiency testing or alternative assessment, personnel competency, document control, corrective action and change control. CLIA's quality system requirements for nonwaived testing are in 42 CFR Part 493 Subpart K, and they apply to LDTs the same way they apply to any other test. Change control is the part that matters most for LDTs, because the laboratory itself owns the design and every change to reagents, instruments, software or procedure can affect the validated performance. Sound Lab Consultants works with labs to build LDT quality plans and change control procedures that hold up at survey.
Last reviewed: Oct 30, 2026
The CLIA rules behind LDT quality management
| Element | CLIA section | Key point |
|---|---|---|
| Performance specifications | 493.1253 | Validation sets the baseline; calibration and control procedures are set from it |
| Calibration and calibration verification | 493.1255 | Calibration verification at least once every 6 months and when specified events occur, where applicable |
| Control procedures | 493.1256 | QC appropriate to the test, documented and reviewed |
| Proficiency testing for unregulated analytes | 493.1236(c) | Verify accuracy at least twice annually for tests without required PT |
| Competency | 493.1235 | Policies to assess employee competency |
| Corrective action | 493.1282 | Documented corrective action when problems are found |
| Records | 493.1105 | Retention of procedures, QC and test records |
| Procedure manual | 493.1251 | Written procedures for each test |
Ongoing oversight checklist
- QC procedures set from the validation results (493.1253(b)(3)) and reviewed on a defined schedule.
- Calibration and calibration verification schedules where the method requires them.
- Proficiency testing enrollment, or a documented alternative assessment at least twice a year.
- Personnel training and competency assessment for the test.
- Document control for procedures, forms and software versions.
- Review of QC trends, PT results, complaints and nonconformances with corrective action.
- Periodic director review of the test, its performance and its literature.
- A change control log for every LDT.
Change control for LDTs
Any change to a validated LDT should be assessed before it is used for patient testing. A good change record states the change, the reason, the performance characteristics it could affect, the studies needed, the acceptance criteria, the results and the approval.
| Change | Typical assessment |
|---|---|
| New reagent lot | Lot-to-lot comparison against defined criteria |
| New reagent supplier or critical component | Risk assessment; often partial revalidation of affected characteristics |
| New instrument or relocation | Comparison and precision checks; calibration verification |
| Software or bioinformatics pipeline version | Re-run a reference data set; revalidate affected outputs |
| New specimen type or collection device | Treat as a new claim and validate under 493.1253(b)(2) |
| Cutoff or algorithm change | Revalidate affected characteristics and update reports |
| Procedure wording only | Document control; confirm no performance impact |
Records to keep
- Validation file and summary with director approval.
- QC records and QC review sign-offs.
- Calibration and calibration verification records.
- PT results or alternative assessment records with any investigation.
- Competency assessments.
- Corrective action records.
- Change control log and every revalidation study.
- Superseded procedures, kept at least 2 years after discontinuation (493.1105).
Common findings, framed generally
- A reagent supplier or software version changed with no record of assessment.
- Alternative assessment done once a year instead of at least twice.
- QC rules not derived from the validation data.
- Corrective action closed without evidence the fix worked.
- Competency records missing for staff who run the LDT.
Worked example: a bioinformatics update
A lab running a sequencing LDT upgrades its variant-calling software. Under change control, the quality lead logs the change, the director identifies accuracy, precision and analytical sensitivity as at risk, and the team re-runs a stored set of previously characterized samples through the new version. Results are compared with the original calls against criteria written before the run. The pipeline goes live only after the director signs the summary, and the procedure and version record are updated. Patient testing continues on the old version until then.
Related pages
See CAP Checklist Requirements for Laboratory Developed Tests, modified FDA-cleared tests, LDT validation and the LDT consulting overview. See also our clinical laboratory consulting, CLIA consultant and full-service laboratory consulting services.
Frequently asked questions
What is LDT change control?
A documented process to assess, test and approve changes to a validated LDT before patient use.
When does an LDT need revalidation?
When a change could affect a performance characteristic, such as a new specimen type, instrument, critical reagent, software version, cutoff or algorithm. The extent depends on the risk.
What CLIA rules cover the LDT quality system?
42 CFR Part 493 Subpart K covers the quality system for nonwaived testing, including 493.1253, 493.1255, 493.1256 and 493.1282.
What if there is no PT program for my LDT?
493.1236(c) requires the lab to verify accuracy at least twice annually for tests without required PT, for example by split-sample or blinded sample testing.
How often is calibration verification required?
Where it applies, 493.1255 requires calibration verification at least once every 6 months and whenever specified events occur.
How long must records be kept?
493.1105 sets minimum retention periods, including at least 2 years after a procedure is discontinued. Accreditors and states may require longer.
Who signs off on LDT changes?
The laboratory director or delegated qualified personnel, per your quality plan.
Can SLC write our LDT change control procedure?
Yes. SLC drafts and reviews quality and change control procedures for your lab to adopt.
Sources
- 42 CFR Part 493 Subpart K - Quality System for Nonwaived Testing (eCFR)
- 42 CFR 493.1253 - Establishment and verification of performance specifications (eCFR)
- 42 CFR 493.1255 - Calibration and calibration verification (eCFR)
- 42 CFR 493.1256 - Control procedures (eCFR)
- 42 CFR 493.1236 - Evaluation of proficiency testing performance (eCFR)
- 42 CFR 493.1235 - Personnel competency assessment policies (eCFR)
- 42 CFR 493.1282 - Corrective actions (eCFR)
- 42 CFR 493.1105 - Retention requirements (eCFR)
- College of American Pathologists - Laboratory Accreditation Program
- CMS - Clinical Laboratory Improvement Amendments (CLIA)
Related LDT pages
- Laboratory Developed Test (LDT) Consulting
- LDT Validation: CLIA Performance Specifications for Laboratory Developed Tests
- LDT Design and Development: Building a Laboratory Developed Test
- LDT Regulatory Oversight and FDA Status
- CAP Checklist Requirements for Laboratory Developed Tests
- NYS CLEP LDT Approval for Laboratory Developed Tests
- Modified FDA-Cleared Tests: When a Modification Makes an LDT
- Laboratory Developed Tests FDA Ruling: Current Status After the 2025 Vacatur