A survey-prepared lab is one that can produce, on request, current evidence that it meets 42 CFR Part 493 and its accreditor's standards. This checklist covers the areas surveyors review: QC and IQCP, quality assessment, procedure manual, calibration and maintenance, proficiency testing, personnel, facility and safety, and certificates and records, each tied to the regulation that requires it.

Last reviewed: Oct 31, 2026

Book a free consultation

Clipboard checklist with several items checked

What survey-prepared means

CMS surveyors follow the procedures in SOM Appendix C, and accreditors use their own published requirements, such as the CAP checklists. A survey-prepared lab keeps its records current all year, so survey preparation is a review, not a rebuild. Use the list below as a self-check, then fix each gap with evidence.

The checklist

Quality control and QC plan

  • ☐ QC run at the required frequency for every test system (493.1256)
  • ☐ IQCP risk assessment, QC plan and QA documented where IQCP is used (SOM Appendix C)
  • ☐ QC reviewed, signed and dated; failures tied to corrective action (493.1282)

Quality assessment

  • ☐ QA reviews for general systems and each testing phase (493.1239, 493.1289)
  • ☐ Indicators tracked and problems followed to closure

Procedure manual

  • ☐ Procedure for every test (493.1251)
  • ☐ Director approval signature and date on new and changed procedures
  • ☐ Retired procedures kept per 493.1105

Calibration and maintenance

  • ☐ Maintenance and function checks per manufacturer (493.1254)
  • ☐ Calibration and calibration verification records (493.1255)
  • ☐ Temperature and environmental logs

Proficiency testing

  • ☐ Enrolled for every regulated analyte
  • ☐ Every event reviewed and signed; corrective action for failures (493.1236)
  • ☐ Twice-yearly accuracy checks for tests without PT

Personnel

  • ☐ Qualifications documented for director and staff
  • ☐ Competency assessments current (493.1235 and personnel subpart)

Facility and safety

  • ☐ Space, ventilation and storage support testing (493.1101)
  • ☐ Exposure control plan (29 CFR 1910.1030) and chemical hygiene plan (29 CFR 1910.1450) current
  • ☐ Reagents labeled and in date

Certificates and records

  • ☐ CLIA certificate type and test menu match testing performed
  • ☐ Records retained for required periods (493.1105)
  • ☐ Prior survey plans of correction and evidence on file

How to use the checklist

  1. Assign each section to a named person.
  2. Mark items as met, partly met or not met, and note the record that proves it.
  3. Put every partly met or not met item on a dated work plan.
  4. Re-check closed items before the survey window.
  5. Keep the completed checklist with your quality assessment records.
Balance scale with specimen tubes, illustrating weighing evidence against requirements

Common gaps found during survey preparation

  • QC data present but no documented review.
  • Procedures in use that the current director never signed.
  • PT events with passing scores but no review record.
  • Calibration verification missed after a reagent lot or major maintenance change.
  • Competency assessments missing one of the required elements.
  • Safety training records out of date.

Accreditor-specific checks

CAP-accredited labs should run the checklist against the current CAP checklist edition for their disciplines. COLA and ACHC labs should use the current criteria or standards from those organizations. All are built on CLIA, so the items above apply to every lab performing non-waived testing.

How SLC helps

Sound Lab Consultants works with labs to run this checklist, document gaps and close them before the survey. See Lab Survey Preparation and Laboratory Survey Management.

Frequently asked questions

What is a survey-prepared lab?

A lab that can show current records proving it meets 42 CFR Part 493 and its accreditor's standards whenever a surveyor asks. Source: eCFR 42 CFR Part 493 - Laboratory Requirements, eCFR 42 CFR § 493.1773.

Which regulations does the checklist follow?

It follows 42 CFR Part 493, including 493.1101, 493.1105, 493.1235, 493.1236, 493.1239, 493.1251, 493.1254, 493.1255, 493.1256 and 493.1289, and the SOM Appendix C survey procedures. Source: eCFR 42 CFR Part 493 - Laboratory Requirements, CMS State Operations Manual Appendix C - Survey Procedures and Interpretive Guidelines for Laboratories (PDF).

Does a CAP lab need a different checklist?

CAP labs should also use the current CAP accreditation checklists for their disciplines. Source: CAP - Accreditation Checklists.

How long must records be kept?

42 CFR 493.1105 sets retention periods; many records, such as QC and PT, must be kept at least two years. Source: eCFR 42 CFR § 493.1105.

Sources

Related pages

Sound Lab Consultants, 25 Arizona Pl, Chandler, AZ 85225.

Book a free consultation

Sound Lab Consultants Logo

Clinical Lab Growth & Compliance Experts helping labs launch, scale, and pass inspections with confidence.

📧 sales@soundlabconsult.com

📍 Headquarters: 25 Arizona Pl, Chandler, AZ 85225
Serving laboratories nationwide in all 50 states

Services

  • CLIA, COLA & CAP Consulting
  • Lab Startup & Buildout
  • Inspection Preparation
  • Lab Billing & Revenue Cycle
  • Staff Training & Compliance

Get Started

Ready to build or scale your lab?

Schedule a Consultation

Trusted by labs nationwide

© 2026 Sound Lab Consultants. All rights reserved.